Data Centers in Fairfax County

“…the increasing demand for data centers and the increased understanding of their potential impacts reveal a need to consider strengthening the County’s current regulations.” (Board of Supervisors March 16, 2024, Meeting Summary)

Since the BOS county-wide decision on data centers does not apply retroactively, the “Plaza 500” data center site-plan review will proceed through the current land-use process under which it will be built “by right”. However, the developer still must abide by the zoning rules for the industrial-zoned property that were in effect when they submitted their site plan application on February 5, 2024.

On January 21, 2025, the Virginia State Corporation Commission (SCC) holds an evidentiary hearing to consider whether to approve or deny Dominion’s application.

Going forward, the County’s changes to the Zoning Ordinance regarding Data Centers in Fairfax will:

  • Limit the size of data centers and where they can be built by right (without explicit Board of Supervisors approval).
  • Require noise studies and noise mitigation to ensure compliance with the County’s existing Noise Ordinance.
  • Impose design standards to improve the aesthetics of data centers.
  • Require screening/enclosure of equipment such as HVAC units and generators.
  • Ensure appropriate distance or “setbacks” from residential neighborhoods.

Future considerations, including energy use and efficiency, will be included with ongoing work to update the Policy Plan in the County’s Comprehensive Plan. The County staff’s reports from January 9 and May 17, 2024, provide detailed analysis of data centers’ impact and recommended policy changes. Additional information and recordings of past community meetings are available on the County’s Data Centers webpage.

For more information on data centers, go to:

For additional information about the Comprehensive Plan amendment on future data centers, call the Fairfax County Zoning Administration Division at 703-324-1314 or email ordadmin@fairfaxcounty.gov

January 20, 2025, the Piedmont Environmental Council met with legislators in Richmond to advocate for “smarter data center development”.

December 19, 2024, a virtual Public Hearing was held by the Virginia State Corporation Commission, which is required to approve, deny, or modify the electrical substation and transmission lines for the proposed Plaza 500 data center. The public was invited to share their concerns and recommendations.

December 5, 2024, an in-person Public Hearing was held by Virginia’s State Corporation Commission, which will approve, deny, or modify the electrical substation and transmission lines for the proposed Plaza 500 data center. The public was invited to share their concerns and recommendations.

September 10, 2024, the Fairfax County Board of Supervisors voted in favor of an amendment to the County zoning ordinance to more strictly regulate data centers going forward, but the ruling did not apply retroactively to the Bren Mar site.

February 5, 2024, Starwood Capital Group submitted a site plan to build a 461,444 sf, 70 ft. tall data center on an currently industrial-zoned site. (Note: On January 23, 2024, Fairfax County Board of Supervisors approved rezoning of a 12-acre plot off Rte 50 for industrial use. The application, submitted by PDCREF 2 Chantilly LLC, a developer affiliated with the D.C.-based firm Penzance, included options for a 150,000-square-foot warehouse or a 402,000-square-foot data center, with heights between 75 and 110 feet.)

March 19, 2024, Board of Supervisors directed County planning staff to prepare a Zoning Ordinance amendment to strengthen the current provisions for data centers and authorized the scheduling of public hearings on an amendment.

May 17, Fairfax County released the Staff Report with the proposed amendments.

June 5, the Planning Commission (PC) held a Public Hearing and voted in favor of the proposed amendments but added further restrictions in line with those requested by residents.

July 16, Board of Supervisors (BOS) held a public hearing and due to the number of speakers, the BOS delayed their vote to July 30. However, due to an oversight of a 2023 Virginia Code regulatory change, a new Public Hearing and vote was held September 10, 2024.

September 10, Board of Supervisors heard public testimony and voted in favor of the amendment to regulate data centers going forward. The Bren Mar Data Center will continue to be built “by right”. The Save Bren Mar coalition is continuing to monitor the development, including the permitting process.

Sign up today to receive the Coalition Update. Updates are only sent to local residents in the Rose Hill Planning District. Emails are kept confidential and not shared. You can request to be removed from the list at any time.

Verified by MonsterInsights